Susa Jinja Sengu

Outline of Sengu

Sengu project plan

  • Main hall roof replacement / Foundation stone masonry repair work, etc.
  • Amaterasu-sha Main hall construction
  • Keidai-sha repair work
  • Worship hall / Shinsen-jo repair work
  • Precinct environment improvement work
  • Preparation of furniture and ritual utensils
  • Execution of various festivals including the Senza-sai festival and celebration festival
  • Other projects related to the enhancement of divine virtues
Main hall Sengu in Heisei 9

Main hall Sengu in Heisei 9 (1997)

Precinct layout map

Sengu event plan

Main hall construction Main hall temporary hall Senza-sai festival April 19, Reiwa 7 (2025)
Main hall construction period April - November Reiwa 7 (2025)
Main hall Sei-Senza-sai festival November 16, Reiwa 7 (2025)
Main hall Hobei-sai festival November 17, Reiwa 7 (2025)
Sengu celebration festival November 22, Reiwa 7 (2025)
Shinjo-sai festival November 23, Reiwa 7 (2025)
Ancillary construction Amaterasu-sha Sengu project Reiwa 8 (2026) - 9 (2027)
Worship hall / Shinsen-jo repair work Reiwa 8 (2026) - 9 (2027)
Keidai-sha repair work Reiwa 7 (2025) - 9 (2027)
Other precinct maintenance work Reiwa 7 (2025) - 9 (2027)
Celebration event for the completion of Sengu Reiwa 9 (2027)